Engineering-Cost-Management-and-Control工程造价管理控制大学毕业论文外文文献翻译及原文

  毕 业 设 计(论文) 外 文 文 献 翻 译

  文献、资料中文题目:工程造价管理控制

  文献、资料英文题目:Engineering Cost Management and Control 文献、资料来源:

  文献、资料发表(出版)日期:

  院 (部):

  专 业:

  班 级:

  姓 名:

  学 号:

  指导教师:

  翻译日期: 2017.02.14

  本科毕业英文文献翻译

  题 目 Research on Construction Project Cost Control Management

  学 院:专业班级:

  学 号:

  学生姓名:

  指导教师姓名:

  指导教师职称:

  年 月 日

  英文原文

  Engineering Cost Management and Control

  Even under the WTO and China's accession to the world community,China's construction industry how to effectively control construction cost of the construction and management of an important component part. However,the current budget for the construction projects - estimate budget,Super budget accounts for the super three is still widespread and that eventually led to a serious loss of control of project investment. Project cost management is the basic contents to determine reasonable and effective control of the project cost.

  As the project cost to the project runs through the entire process, stage by stage can be divided into Investment Decision stage,the design and implementation phases. The so-called Project Cost effective control is the optimization of the construction plans and design programs on the basis of in the building process at all stages,use of certain methods and measures to reduce the cost of the projects have a reasonable control on the scope and cost of the approved limits.

  Engineering and cost management work of the current status of project cost management system was formed in the 1950s, 1980s perfect together. Performance of the country and directly involved in the management of economic activities. Provisions in the design stage to different estimates or budget preparation as well as government; Nothing relevant departments to formulate a budget, content, methods and approval, the budget will provide the fixed cost of equipment and materials and fixed price of the budget preparation, approval, management authority,and so on.

  With the historical process, after recovery, reform and development, formed a relatively complete budget estimate of quota management system. However, as the socialist market economic development, the system's many problems have also exposed. Generally speaking, the budget estimate is based on direct participation in the management of national economic activity as a precondition. Enterprise is not the actual economic entities. Due to the

  characteristics of the planned economy, and, at the time under the conditions of productivity, will inevitably become a shortage in the economy.

  In severe shortage of commodities under the conditions,as long as a certain level of investment,will be certain outputs. In this environment,the project planning and technical argumentation there can be no economic analysis. State control of the project cost constitute key factors equipment and materials prices,wages and taxes of artificial distribution. In this relatively stable economic environment,the budget estimate for the system approved project cost,help the government to carry out investment plans to play a major role.

  As the socialist market economic system established,requires us to predict project investment and control. In recent years,international investment project developed to the requirements of prior pre-control and in the middle of control. China,the traditional practice in

  an objective light on the cause decision-making,implementation heavy,light the economy and technology,

  First, the consequences of victimization, Due to the technical personnel of the project technical and economic concepts and a weak awareness of cost control, cost management makes the quality difficult to raise. Project Cost control is difficult to achieve long-term goals.

  Second,the various stages of the project management view of the above circumstances, My first academia in the 1980s made the whole process of cost management and control concept,building departments will study the feasibility of projects and the budgets and final accounts to two extended at the request of the corresponding regulations put our cost

  management concepts and methods referred to a new height.

  Our task now is to be modern and cost management in line with China's national conditions of the market economy system goal,learn from the advanced experience of the developed countries,and establish sound market economic laws of project cost management system, efforts to increase the project cost levels. An investment decision-making phase of the project cost management construction project investment decision-making stage is proposed project proposals; conduct a feasibility study to determine investment estimation and the final

  preparation of design task. At this stage,the project's technical and economic decision-making, of the construction project cost of the project after the completion of the economic benefits have a decisive influence,The construction cost is an important stage control.

  China's current stage of the project cost for the project management for the purpose of

  clearing price,and focusing only on the construction process of cost control,neglected before the start of the project investment decision-making stage of cost control. Investment

  decision-making phase of investment projects is estimated an important basis for

  decision-making. It has a direct impact on national economic and financial analysis of the results of the reliability and accuracy. Because of this phase is the preliminary work of projects,the information cannot be fully,comparable works more or less that information accumulated

  relatively small,estimated inadequate and unscientific. Makes project cost management and cost workers is difficult at this stage do something.

  The various stages of the project cost control in the decision-making phase project cost control. Right project planning phase of the cost,many owners have the wrong understanding that the lower the cost the better. Cost control is not a unilateral issue,and should be a number of factors,a combination of practical,comprehensive consideration. The construction project investment decision-making stage, the project's technical and economic decision-making, Cost of the project after the completion of the project and the economic benefits,with a decisive role in project cost control is an important stage,rationally define and control the direction of the project cost of accurate positioning and building Optimization guiding role.

  In the decision-making phase of the most important is to do a good job feasibility study, the work is done well,returns on investment and can form a good proportion. Otherwise, invest more,less effective,resulting in loss of control and waste of investment.

  At present,some of the projects planned the owners of departure from the subjective desires of a feasibility study on the lack of scientific proof. Feasibility Study untrue,false or engineering functions obtaining the approval of their superiors,actually put into the feasibility study will be awarded in the study for the project after the smooth functioning buried a lot of hidden

  problems, lead to insufficient follow-up funds for the project and had to extend the time limit so that the project could not have planned the use of cost-effective,even become hopeless completion of the beard works.

  Therefore,in order to phase in the investment decision-making effectively control

  construction costs,we must do the following aspects:

  ⅰImplementation of the construction project and corporate accountability,Construction of the project from planning to implementation of the entire process and the use of the funds to repay responsibilities to the people. in addition to establishing a legal system and the project supervision matching mechanism by the departments in charge of the industry and supervision departments for setting up a monitoring group to oversee the use of funds.

  ⅱA realistic approach to market analysis,to avoid the blindness of the project

  decision-making,reduces and reduces investment risk. Fully consider building projects in the future market competitiveness,design task more scientific and reliability.

  ⅲ Capital financing must have a formal commitment document,the parties must do investment funds in place,and funds must have documents to ensure that the project can be approved after the scheduled implementation. To the various loan conditions should be carefully analyzed to minimize the burden of interest and repayment pressure.

  ⅳ To strengthen the engineering geology,hydrology,geology and land,water,electricity, transport,environmental projects such as external conditions for the work of depth to make the investment estimate there are sufficient grounds.

  Engineering-Cost-Management-and-Control工程造价管理控制大学毕业论文外文文献翻译及原文1

  中文翻译

  工程造价管理控制

  即使在世贸组织和中国加入世界大家庭, 是中国建筑业如何有效地控制工程造价的建设和管理的一个重要组成部分。 然而,目前的年度预算为建设项目-概算,预算,超预算的三超现象仍然普遍存在,最终导致了严重失控项目投资。工程造价管理的基本内容,就是合理确定和有效控制工程造价。

  作为这项工程的费用,以项目贯穿整个过程中, 按阶段可分为:投资决策阶段,设计和实施阶段。 所谓工程造价的有效控制, 在优化建设方案,设计方案的基础上,在建设过程的所有阶段使用某些方法和措施,以降低工程成本有一个合理控制的范围 和成本的核定限额。

  工程造价管理制度形成于50年代, 80年代成熟起来,表现为国家直接参与管理经济活动。规定在设计阶段,以不同的概算或预算的编制以及政府,没有有关部门制订财政预算案、内容、方法和审批, 这份预算案将提供固定费用、设备和材料,采用固定价格的预算编制、审批、管理权限,等等。

  随着历史进程经过恢复、改革和发展,形成了比较完备的概预算定额管理制度。 但是,随着社会主义市场经济的发展,制度的许多问题也暴露出来。一般来说,预算是基于直接参与管理国家的经济活动作为先决条件,企业并不是实际的经济实体,由于特征的计划经济体制,并在当时的条件下,生产力必将成为短缺经济。

  严重的商品短缺的情况下,只要有一定程度的投资将产品产出。在这种环境下,项目的规划和技术论证就不可能有经济分析。国家控制的项目成本构成要素的设备和材料价格。在这种相对稳定的经济环境,财政预算的制度,核定工程造价, 帮助政府进行投资计划方面发挥了重大作用。

  随着社会主义市场经济体制的确立,要求我们以预测项目的投资和控制。近年来,国际投资项目的发展要求,事前预控,事中控制。中国传统的做法,从客观的角度对事业的决策,执行重,轻经济。

  首先,由于技术人员的工程技术和经济观念和意识淡薄 成本控制,成本管理,使质量难以提高。工程造价控制是很难达到的长远目标。

  第二,各个阶段的项目管理鉴于上述情况,我国在八十年代提出了全过程的成本管理与控制的概念,建设部门将进行可行性研究和项目的预算和决算等,以扩大两国的请求的相应规定,我们把成本管理的观念和方法提到了一个新高度。

  我们现在的任务是要与现代成本管理的,符合中国国情的市场经济的系统目标,借鉴先进发达国家的经验, 建立健全市场经济规律的工程造价管理体系,努力提高工程造价的水平。

  投资决策阶段的工程造价管理建设项目投资决策阶段是提出项目建议书, 进行了可行性研究,确定投资估算,最终编制设计任务。在这个阶段,项目的技术和经济决策, 对建设项目工程造价的工程完成后的经济效益有着决定性的影响,建造成本是一个重要的阶段控制。

版权声明:此文档由查字典文档网用户提供,如用于商业用途请与作者联系,查字典文档网保持最终解释权!

下载文档

热门试卷

2016年四川省内江市中考化学试卷
广西钦州市高新区2017届高三11月月考政治试卷
浙江省湖州市2016-2017学年高一上学期期中考试政治试卷
浙江省湖州市2016-2017学年高二上学期期中考试政治试卷
辽宁省铁岭市协作体2017届高三上学期第三次联考政治试卷
广西钦州市钦州港区2016-2017学年高二11月月考政治试卷
广西钦州市钦州港区2017届高三11月月考政治试卷
广西钦州市钦州港区2016-2017学年高一11月月考政治试卷
广西钦州市高新区2016-2017学年高二11月月考政治试卷
广西钦州市高新区2016-2017学年高一11月月考政治试卷
山东省滨州市三校2017届第一学期阶段测试初三英语试题
四川省成都七中2017届高三一诊模拟考试文科综合试卷
2017届普通高等学校招生全国统一考试模拟试题(附答案)
重庆市永川中学高2017级上期12月月考语文试题
江西宜春三中2017届高三第一学期第二次月考文科综合试题
内蒙古赤峰二中2017届高三上学期第三次月考英语试题
2017年六年级(上)数学期末考试卷
2017人教版小学英语三年级上期末笔试题
江苏省常州西藏民族中学2016-2017学年九年级思想品德第一学期第二次阶段测试试卷
重庆市九龙坡区七校2016-2017学年上期八年级素质测查(二)语文学科试题卷
江苏省无锡市钱桥中学2016年12月八年级语文阶段性测试卷
江苏省无锡市钱桥中学2016-2017学年七年级英语12月阶段检测试卷
山东省邹城市第八中学2016-2017学年八年级12月物理第4章试题(无答案)
【人教版】河北省2015-2016学年度九年级上期末语文试题卷(附答案)
四川省简阳市阳安中学2016年12月高二月考英语试卷
四川省成都龙泉中学高三上学期2016年12月月考试题文科综合能力测试
安徽省滁州中学2016—2017学年度第一学期12月月考​高三英语试卷
山东省武城县第二中学2016.12高一年级上学期第二次月考历史试题(必修一第四、五单元)
福建省四地六校联考2016-2017学年上学期第三次月考高三化学试卷
甘肃省武威第二十三中学2016—2017学年度八年级第一学期12月月考生物试卷

网友关注视频

【获奖】科粤版初三九年级化学下册第七章7.3浓稀的表示
【部编】人教版语文七年级下册《过松源晨炊漆公店(其五)》优质课教学视频+PPT课件+教案,辽宁省
冀教版小学数学二年级下册第二周第2课时《我们的测量》宝丰街小学庞志荣.mp4
【部编】人教版语文七年级下册《逢入京使》优质课教学视频+PPT课件+教案,安徽省
化学九年级下册全册同步 人教版 第25集 生活中常见的盐(二)
19 爱护鸟类_第一课时(二等奖)(桂美版二年级下册)_T3763925
冀教版英语五年级下册第二课课程解读
苏教版二年级下册数学《认识东、南、西、北》
北师大版八年级物理下册 第六章 常见的光学仪器(二)探究凸透镜成像的规律
沪教版牛津小学英语(深圳用) 五年级下册 Unit 10
冀教版小学数学二年级下册第二单元《有余数除法的整理与复习》
七年级英语下册 上海牛津版 Unit9
《空中课堂》二年级下册 数学第一单元第1课时
【部编】人教版语文七年级下册《逢入京使》优质课教学视频+PPT课件+教案,安徽省
第19课 我喜欢的鸟_第一课时(二等奖)(人美杨永善版二年级下册)_T644386
二年级下册数学第一课
飞翔英语—冀教版(三起)英语三年级下册Lesson 2 Cats and Dogs
外研版八年级英语下学期 Module3
沪教版牛津小学英语(深圳用) 六年级下册 Unit 7
精品·同步课程 历史 八年级 上册 第15集 近代科学技术与思想文化
二年级下册数学第二课
第五单元 民族艺术的瑰宝_15. 多姿多彩的民族服饰_第二课时(市一等奖)(岭南版六年级上册)_T129830
河南省名校课堂七年级下册英语第一课(2020年2月10日)
冀教版小学数学二年级下册第二单元《有余数除法的竖式计算》
冀教版小学数学二年级下册第二单元《余数和除数的关系》
沪教版牛津小学英语(深圳用) 五年级下册 Unit 7
冀教版小学数学二年级下册第二周第2课时《我们的测量》宝丰街小学庞志荣
苏科版数学七年级下册7.2《探索平行线的性质》
第五单元 民族艺术的瑰宝_16. 形形色色的民族乐器_第一课时(岭南版六年级上册)_T1406126
北师大版数学四年级下册第三单元第四节街心广场