  科技外文文献

  Discussing about the successful factors of

  ERP projects implementation and the risk management

  Refers to the overseas some literature material, a successful ERP project, often needs to spend several year times, number thousands of US dollars can complete. Again turns head looks at the home, along with ERP skepticisms gaining ground, price war starting, ERP took one kind of software supplier's product, has actually goes down the god world tendency. ERP leader SAP also promoted Business the One product, the price has been lower than 100,000.Even if the ERP software can achieve free, or like the IBM esteem according to the boundary which must collect fees, implements the angle from the entire enterprise, considers the personnel, training, the maintenance, the service reorganization, the re-development, three, n development, its expense should also in several 1,000,000 and even surely the scale. This speaking of the domestic enterprise, already was not the small number.

  But, some many enterprises harbor the beautiful dream, steps the ERP implementation the difficult travel. In which also has many projects to be defeated comes to an end. But regarding these final survivors, whether can the halberd be also put in storage, drinks wine to sing loudly? In fact, the enterprise implements the ERP project after the success will face implements a bigger risk. In future five to ten years in, some solid ERP risk management mechanism had decided whether the enterprise can obtain benefits truly in the initial ERP investment. In 1998 Thomas H.Davenport has published named Puts in Enterprise System the article in the Harvard commerce commentary (Putting the enterprise into the enterprise system).This article proposed systematically the enterprise system, or called the ERP system the operation brings for the enterprise

  to the project advantageous or the disadvantageous element of certainty. The project is for completes the disposable endeavor which some unique product or the service station do, the project the distinctive quality had decided the project not impossible was by with the before identical way, simultaneously, the project which completed by and the before identical person must create the product or the service, as well as the project possibly involved the scope, the time and the cost all not impossible started when the project completely to determine, therefore, carried on in the process in the project also corresponding to be able to appear the massive uncertainty, namely project risk. Below this article mentioned the risk is refers to the project disadvantageously the element of certainty. Exists to the project disadvantageous risk in any project, often and can give the project the advancement and the project success brings the negative influence. Once the risk occurs, its influence is various, like causes the project product/service the function to be unable to satisfy the customer the need, the project expense surpasses the budget, the project plan dragging or is compelled to cancel and so on, it finally manifests for customer degree of satisfaction depression. Therefore, the recognition risk, the appraisal risk and take the measure to be supposed to be the risk management have the extremely vital significance to the risk to the project management.

  Ⅰ Risk management concrete content

  The project risk management mainly divides into following several steps: The risk recognition, the qualitative/quota risk analysis, the risk should to plan the establishment and the risk monitoring.

  1. risk recognitions

  The risk recognition, is refers distinguishes and records possibly has the adverse effect to the project the factor. Because the project is in develops in unceasingly the change process, therefore the risk recognition also passes through in the entire project implementation entire process, but is not merely the project initial stage. The risk recognition is not the disposable work, but need more systems, crosswise thought. Possesses nearly about the project plan and the information all possibly takes the risk recognition the basis, like project progress and cost plan, work decomposition structure, project organizational structure, project scope, similar project historical information and so on. Needs to pay attention, all risks all may carry on the management by no means through the risk recognition. The risk recognition only can discover the known risk (for example: In the known project organization some member ability cannot satisfy the request completely) or the known unknown risk (known-unknown, namely event name known, like customer side personnel participates in dynamics being insufficient Before but certain risks, as a result of the project distinctive quality, not impossible to occur in it know in advance (unknown-unknown, namely unknown-unknown risk).

  2. qualitative/quota risk analysis

  The latent risk quantity distinguishes which through the risk recognition process are very many, but these latent risks to the project the influence are various. The risk analysis namely through the analysis, the comparison, the appraisal and so on each way, to determined various risks the importance, sorts to the risk and appraises it to the project possible consequence, thus causes the project to implement the personnel to be possible to concentrate the main energy in the few in number main risk, thus enable the project the overall risk to be under the effective

  control.

  The risk analysis mainly may use the method includes: Risk probability/influence appraisal matrix, sensitive analysis, simulation and so on. When carries on the above analysis, mainly pays attention to following several risk factor:

  Risk probability: Namely the risk event occurs possible percentage expression. This numeral is, like the expert who obtains through the subjective judgment appraises, the interview or the basis before similar project historical information.

  Risk influence: Namely the risk has possibly the influence size which creates to the project. This kind of influence is possibly in the time, possibly is in the cost, also is possibly other various aspects. Risk value (required value EMV): The risk value = risk probability * risk influence, is to the risk the influence most direct appraisal which creates to the project, its overall evaluation probability with has affected two aspects the factors.

  3. risks should plan the establishment

  The risk should lie in to the plan goal through the formulation corresponding measure, comes to be supposed to the risk the threat which possibly creates to the project.Most often uses should to threat several measures be: The circumvention, reduces, the shift, accepts. The circumvention, namely eliminates this risk through the elimination risk origin;

  Reduces, namely through takes the measure to reduce the risk probability or the risk influence, thus achieved reduces the risk value the result;

  The shift, soon the risk shifts to another side, like purchase insurance, sub package and so on;

  Accepts, namely does not take the measure to this risk, accepts result

  which it creates, or occurs after this risk uses the contingency plan to carry on processing again. Selects what method to come specifically to be supposed to some risk, is decided in this risk value (EMV), plans to adopt should to the measure possible cost, the project management personnel treat the risk the manner (utility function) the type and so on various aspects, cannot be generally spoken.

  The risk should be aims at the risk to the plan which distinguishes to carry on; Regarding the unknown risk, not impossible to choose in advance the formulation corresponding to be supposed to plan or the contingency

  plan, therefore, may stockpile using the management should be right.

  4. risk monitoring

  The risk monitoring mainly includes following several aspects the duty:

  1) Carrying on in the process in the project to track has distinguished the risk, the monitoring remaining risk and distinguishes the new risk: Along with the project implementation as well as the risk should to the measure execution, each kind the influence factor be in the process to the project which changes unceasingly, therefore, needs in the entire project process, the time surveillance risk development and the change situation, determined follows the new risk which certain risks vanishing comes and formulates the corresponding processing measure.

  2) Guaranteed the risk should to the plan execution and appraised the risk should to plan carry out the effect. The appraisal method may be the project cycle (stage) the natural review, the achievements appraisal and so on.

  3) accepts to the sharp-edged risk the risk takes the suitable flexible measure. Through the risk monitoring process, the project personnel renews the project risk tabulation continually, and through the repetition above various steps guaranteed the project risk is at the controlled condition throughout.

版权声明:此文档由查字典文档网用户提供,如用于商业用途请与作者联系,查字典文档网保持最终解释权!

下载文档

热门试卷

2016年四川省内江市中考化学试卷
广西钦州市高新区2017届高三11月月考政治试卷
浙江省湖州市2016-2017学年高一上学期期中考试政治试卷
浙江省湖州市2016-2017学年高二上学期期中考试政治试卷
辽宁省铁岭市协作体2017届高三上学期第三次联考政治试卷
广西钦州市钦州港区2016-2017学年高二11月月考政治试卷
广西钦州市钦州港区2017届高三11月月考政治试卷
广西钦州市钦州港区2016-2017学年高一11月月考政治试卷
广西钦州市高新区2016-2017学年高二11月月考政治试卷
广西钦州市高新区2016-2017学年高一11月月考政治试卷
山东省滨州市三校2017届第一学期阶段测试初三英语试题
四川省成都七中2017届高三一诊模拟考试文科综合试卷
2017届普通高等学校招生全国统一考试模拟试题(附答案)
重庆市永川中学高2017级上期12月月考语文试题
江西宜春三中2017届高三第一学期第二次月考文科综合试题
内蒙古赤峰二中2017届高三上学期第三次月考英语试题
2017年六年级(上)数学期末考试卷
2017人教版小学英语三年级上期末笔试题
江苏省常州西藏民族中学2016-2017学年九年级思想品德第一学期第二次阶段测试试卷
重庆市九龙坡区七校2016-2017学年上期八年级素质测查(二)语文学科试题卷
江苏省无锡市钱桥中学2016年12月八年级语文阶段性测试卷
江苏省无锡市钱桥中学2016-2017学年七年级英语12月阶段检测试卷
山东省邹城市第八中学2016-2017学年八年级12月物理第4章试题(无答案)
【人教版】河北省2015-2016学年度九年级上期末语文试题卷(附答案)
四川省简阳市阳安中学2016年12月高二月考英语试卷
四川省成都龙泉中学高三上学期2016年12月月考试题文科综合能力测试
安徽省滁州中学2016—2017学年度第一学期12月月考​高三英语试卷
山东省武城县第二中学2016.12高一年级上学期第二次月考历史试题(必修一第四、五单元)
福建省四地六校联考2016-2017学年上学期第三次月考高三化学试卷
甘肃省武威第二十三中学2016—2017学年度八年级第一学期12月月考生物试卷

网友关注视频

人教版二年级下册数学
冀教版小学数学二年级下册第二周第2课时《我们的测量》宝丰街小学庞志荣
冀教版小学英语四年级下册Lesson2授课视频
七年级英语下册 上海牛津版 Unit3
【部编】人教版语文七年级下册《逢入京使》优质课教学视频+PPT课件+教案,安徽省
冀教版小学数学二年级下册第二单元《余数和除数的关系》
沪教版牛津小学英语(深圳用) 五年级下册 Unit 12
冀教版英语四年级下册第二课
8.对剪花样_第一课时(二等奖)(冀美版二年级上册)_T515402
精品·同步课程 历史 八年级 上册 第15集 近代科学技术与思想文化
【部编】人教版语文七年级下册《过松源晨炊漆公店(其五)》优质课教学视频+PPT课件+教案,辽宁省
沪教版牛津小学英语(深圳用) 四年级下册 Unit 4
第五单元 民族艺术的瑰宝_16. 形形色色的民族乐器_第一课时(岭南版六年级上册)_T1406126
【部编】人教版语文七年级下册《泊秦淮》优质课教学视频+PPT课件+教案,广东省
苏教版二年级下册数学《认识东、南、西、北》
【部编】人教版语文七年级下册《逢入京使》优质课教学视频+PPT课件+教案,辽宁省
沪教版八年级下册数学练习册21.4(1)无理方程P18
3月2日小学二年级数学下册(数一数)
北师大版八年级物理下册 第六章 常见的光学仪器(二)探究凸透镜成像的规律
8 随形想象_第一课时(二等奖)(沪教版二年级上册)_T3786594
小学英语单词
沪教版八年级下次数学练习册21.4(2)无理方程P19
沪教版八年级下册数学练习册一次函数复习题B组(P11)
【部编】人教版语文七年级下册《老山界》优质课教学视频+PPT课件+教案,安徽省
外研版英语七年级下册module3 unit2第二课时
冀教版英语三年级下册第二课
二年级下册数学第二课
人教版历史八年级下册第一课《中华人民共和国成立》
沪教版牛津小学英语(深圳用) 四年级下册 Unit 3
河南省名校课堂七年级下册英语第一课(2020年2月10日)